Friday, November 27, 2026
Late edition · Updated as it breaks
Log inSubmit a story

“All the news worth catching.”

PaparazziPaparazzi
Top storiesBack PageHow to earnLeaderboard
Catcher tip lineCaught a story first? Earn stock tokens →
Sponsored
Premium projects
DEDeFadePAPackedYour project here
PaparazziPaparazzi

All the news worth catching.

Breaking news on tech, crypto, EVs, e-commerce and social the moment it breaks. Written by AI from verified reporting.

SectionsTop storiesRobinhood ChainTech & AIE-commerceWeb3 & CryptoEV & EnergyGlobal & SocialEntertainmentGamingSportsBusiness & marketsHealth & sciencePolitics & world
EarnStart hereSubmit a storyGTA WeekHow to earnLeaderboardContestsCatcher desksTop catchers by reputationAssignmentsLeagueNews bountiesCityMy catchesRewards
MarketsLive statsProof of payoutsWhale watchDeep Scan token checksStock fundHolder perksRobinhood Chain launchesRobinhood Chain projectsList your projectPremium project pagesPartnersThe Chain WeeklyRobinhood Chain Daily
PaparazziPaparazzi InkPaparazzi Ink top writersOpinionLive coverageEvents calendarThe Back PageSuggest a Back Page storyPaparazzi on TelegramHow it worksFAQProof of workAbout usHow we score trustEditorial policyPrivacy policyTerms of serviceCorrectionsAccuracy recordRelease notesAdvertiseMedia kitNews APIContact
$PAPA contract · Robinhood Chain
© 2026 Paparazzi

Written by AI from verified reporting. Not financial advice.

  • Home
  • Submit
  • Earn
  • Sign in
Top storiesRobinhood ChainTech & AIE-commerceWeb3 & CryptoEV & EnergyGlobal & SocialEntertainmentGamingSportsBusiness & marketsHealth & sciencePolitics & worldWhales
EV & Energy
Important, importance 61 of 100

TEPCO bets ¥10.2T on nuclear and grid to feed Japan's AI data centers

TEPCO plans to spend ¥10.2 trillion through fiscal 2035 on power grids and nuclear plants, wagering that AI data centers will foot the bill. The utility expects data center electricity sales to climb nearly eightfold and EBITDA to nearly double. Fukushima cleanup costs and a delayed reactor restart hang over the plan.

By the Paparazzi desk November 26, 2026 · 11:18 PM · cryptobriefing.com · 1 view
Fact boxTrust 50/100 · Developing
What we verified
  • Original source: cryptobriefing.com.
  • The source published it on Nov 26, 2026 at 11:18 PM.
What we couldn't
  • No second outlet has reported it yet. Treat it as a single-source claim.

Tokyo Electric Power Company Holdings plans to spend ¥10.2 trillion through fiscal 2035 on power grids and nuclear plants, a bet that AI data centers will buy enough electricity to pay for reactor restarts, network upgrades and the Fukushima cleanup. The money splits into two main buckets: ¥4.9 trillion for transmission and distribution networks, and ¥2.5 trillion for nuclear upgrades and added capacity. For a utility still defined by the 2011 Fukushima Daiichi disaster, it's a sharp change in tone — TEPCO is now pitching itself as the go-to power supplier for Japan's AI buildout.

The demand forecast behind the spending is aggressive. TEPCO expects electricity sales to data centers to climb nearly eightfold, reaching roughly 340 billion kWh by fiscal 2035 from about 43 billion kWh in fiscal 2027. On the money side, it projects EBITDA after decommissioning payments could nearly double, hitting ¥1.44 trillion. And ¥10.2 trillion may not be the ceiling — the plan's longer-range outlook says cumulative spending may exceed ¥15 trillion by fiscal 2040.

Sponsored

Nuclear is moving, but slowly. Unit 6 at the Kashiwazaki-Kariwa plant restarted in April 2026, the first TEPCO reactor back online since Fukushima. Unit 7 at the same site slipped to a targeted restart around April 2031 after construction problems with a required antiterrorism facility. TEPCO wants carbon-free power to make up 60% of its mix by 2040, up from around 20% in 2024.

Paying for all of it is the open question. TEPCO must keep covering costs tied to the Fukushima Daiichi meltdown, a cleanup estimated at ¥23 trillion industry-wide. On November 25, 2026, the company disclosed it is negotiating with five investor groups — SoftBank among them — about potential capital alliances, with no definitive agreements made public so far.

Three things to watch: whether any deal with the five investor groups gets signed, progress on the Kashiwazaki-Kariwa antiterrorism facility, and whether actual data center sales in fiscal 2027 land anywhere near that 43 billion kWh starting point. That early number is the first real test of the eightfold forecast.

TopicsTEPCO · Tokyo Electric Power Company Holdings · SoftBank · Kashiwazaki-Kariwa · Fukushima Daiichi · Japan

Share

Source: cryptobriefing.com

Written by AI from verified reporting.

More stories

  • EV & Energy 23:16 UTC · 2 hours ago · cryptobriefing.com
    Tesla-SpaceX merger chatter puts Tesla stock in a holding pattern
  • EV & Energy 22:16 UTC · 3 hours ago · x.com
    Musk says he'll give every US child a SpaceX share each year
  • EV & Energy 20:16 UTC · 5 hours ago · x.com
    Polymarket Traders Give Tesla-SpaceX Merger a 55% Chance by 2027
  • EV & Energy 12:31 UTC · 12 hours ago · electrive.com
    Spain's EV subsidy pot hits empty as election freezes any refill
Catcher tip line

Caught a story we missed?

Log in and send it in. If it checks out, it runs with your name on it and you earn stock tokens. The bigger the story, the bigger the reward.

Submit a story
The newsletter

Get the paper in your inbox.

A short digest of the biggest news, plus optional breaking alerts. Free, no account needed.