Solar and storage mega-project to power U.S. Steel's Arkansas expansion
The Steel River Energy Center — 2.46 gigawatts of solar and 2.94 gigawatt-hours of batteries — broke ground in Arkansas this July with $4.5 billion in private backing. Cypress Creek Energy is building it, Google is buying the first two phases' output, and U.S. Steel's $3.5 billion Big River Steel 2 mill sits one mile away.
- Original source: canarymedia.com.
- The source published it on Nov 19, 2026 at 8:30 AM.
- No second outlet has reported it yet. Treat it as a single-source claim.
Construction crews broke ground this past July on the Steel River Energy Center, a 2.46-gigawatt solar array paired with 2.94 gigawatt-hours of battery storage in Northeast Arkansas. Cypress Creek Energy is developing the project and will own and operate it across three phases, with full operation expected in 2029. The company calls it the largest solar-plus-storage project in America. Entergy Arkansas will connect the facility to its transmission grid.
The numbers behind it are big. Cypress Creek puts the private investment at $4.5 billion, with 1,400 construction jobs across the first two phases and $300 million in local tax revenue over the project's lifetime. Google signed a power purchase agreement to take the energy from those first two phases, making Steel River the largest solar-and-storage project the company has sourced power from anywhere in the world.
The offtake matters because of who's next door. U.S. Steel spent close to $3.5 billion on Big River Steel 2 in Osceola, Arkansas — the biggest single investment in its 125-year history — and built it one mile from its existing Big River Steel mill, which can churn out more than 3 million tons of steel a year. Dan Brown, U.S. Steel's executive vice president of advanced technology steelmaking and CEO of Big River Steel, said the site hunt covered 48 states before narrowing to 20, then 10, five and three. Reliable, affordable electricity, he said, is either the first or second factor on that list.
Steel River is also a domestic manufacturing story. The project is being built with 100% U.S.-made structural steel, including roughly 400,000 steel piles supporting more than 3 million solar panels. PACO Steel fabricates those piles in nearby Blytheville, Arkansas from coils rolled at the Big River Steel 2 mill; each one carries a stamp reading 'Proudly made in Mississippi County.' First Solar's U.S. factories supply the panels, California-based Nextpower builds trackers with domestic steel, and LG Energy Solution Vertech assembles the battery systems domestically using cells made in North America.
Cypress Creek CEO Kevin Smith said solar and storage have moved past their niche era. 'Steel River is proof that solar and storage have crossed a threshold,' he said, arguing the project can beat alternatives on price and speed. The model travels, he added: not every site can host gigawatts, but 100-to-500-megawatt blocks can be built across Arkansas, the Midwest, the Southeast and the West. Smith credited economics rather than ideology for the wave of renewable manufacturing landing in red states — 'It's not about ideology,' he said. 'It's arithmetic.'
Brown, who lives five minutes from the Osceola mill, said the effects are already visible locally: more restaurants, more people in town, more spending at the stores.
TopicsU.S. Steel · Big River Steel · Cypress Creek Energy · Google · First Solar · PACO Steel · Nextpower · Entergy Arkansas
Source: canarymedia.com
Written by AI from verified reporting.
More stories
- EV & Energy cleantechnica.com 2 viewsFranco-German car deal covers only 13% of Europe's 2030 battery cells, T&E warns
- EV & Energy electrek.co Caught by @martin 1 viewIEA: Hormuz Oil Shock Could Supercharge EVs and Solar
- EV & Energy x.com 4 sources 1 viewMusk Says a Tesla Model Y With No Steering Wheel Is on the Way
- EV & Energy electrek.co 2 viewsToyota's C-HR EV recall swells to 19,000 cars worldwide